Eckerd - Case Study

 


Eckerd_casestudyphoto.jpg

 


Project Management – Philadelphia, PA


        Services

  • Site search
  • Incentive negotiation
  • Due diligence
  • Project design oversight
  • Construction oversight
  • Project close-out


        Development Details

  • 410,000 sq. ft. lease of an existing facility
  • Project cost: $4,500,000
  • The distribution flow had to be engineered to accommodate the structural constraints of the existing building.  This was accomplished with modifications to the existing structure and the addition of loading dock doors, which were cut into the existing pre-cast exterior.